Lean Construction · Term
Percent Plan Complete (PPC)
Definition
PPC stands for Percent Plan Complete: the share of a week's commitments that were actually completed. In German-speaking projects the metric is known as AEZ. It does not measure output, it measures reliability. It shows the team how well it plans and commits, and it is the starting point for asking why commitments stayed open.

- Related pages
- 3
- In depth
- Last Planner System
In context
What does Percent Plan Complete (PPC) mean in construction?
PPC is the key metric of the Last Planner System. Every week it shows how reliable the commitments were.
Worked example
18 of 24 commitments completed gives a PPC of 75%. The team discusses the reasons for the six open commitments in its review.
PPC = commitments completed in the week divided by all commitments of the week, times 100%
Further reading
Related pages
A question about your project?
PLACE is a Lean Construction consultancy from Germany, based in Cologne and Stuttgart. We coach project teams until they work with methods such as the Last Planner System on their own; responsibility for the project stays with the team. Write to us or call us, in English or German. We usually reply within one working day.