Last Planner System (LPS): collaborative construction planning explained

- Key metric
- Percent Plan Complete (PPC)
- Rhythm
- weekly, with a six-week lookahead
- Used in
- Building, civil and infrastructure works, from a single trade package to a major project
What is the Last Planner System?
A Lean Construction method for planning construction work: the people who do the work commit themselves to what will be finished.
The name comes from the ‘last planners’: the people who make the final assignment of work, such as foremen and site supervisors of the trades and, in design, the architects and engineers. They commit to what will be finished in the coming week, instead of working towards a date handed down to them. Variances are discussed every week without blame, so each round becomes more reliable.

How does the Last Planner System work?
In five steps, from master scheduling to learning. Lookahead, weekly work plan and learning repeat every week.
Steps 03 to 05 run anew every week.
Step 01
Master scheduling
Milestones set the frame of the project. In German practice the team also maps the whole delivery process in the Big Room at this stage (Gesamtprozessanalyse, overall process analysis): waste, duplicated work and waiting times become visible.
- What happens
- Everyone involved draws up a process map together that shows every interface.
- What for
- Make processes visible and see where time and money are lost.
How does it differ from traditional scheduling?
Planning runs from the bottom up: firm commitments from the people who do the work instead of dates handed down.
What are the benefits of the LPS?
More reliable schedules, less downtime and rework, clearer communication and a learning curve from week to week.
How can you tell whether the LPS is working?
By Percent Plan Complete (PPC): the share of committed tasks that were completed in the week.
Percent Plan Complete (PPC)=commitments completed in the weekall commitments for the week× 100%
Work it out yourself
The 6 open commitments go into the weekly review, each with its reason.
Metrics and tools
Percent Plan Complete (PPC)
Percent Plan Complete: the key metric, measured anew every week.
Reasons for variance
Reasons for variance by category, the basis for kaizen.
Make-ready
Removing the constraints on a task before it enters the weekly work plan.
Analogue or digital
Start with sticky notes, later go digital with tools such as Yolean or koppla.
How do you introduce the LPS?
Step by step: train the team, set up a first master schedule, pilot it on a real project.
- Train the team and start with a kick-off workshop
- Draw up a first master schedule with milestones
- Pilot it step by step on real projects
How long the system takes to stabilise depends on the project and the team.
What does the LPS look like on a project?
Two projects that PLACE supported, and what changed there.
‘Since we began working with PLACE […], planning has been far better coordinated. We have considerably shorter planning times on our projects […].’
Joachim Hölzel, Managing Director, BANKWITZ beraten planen bauen GmbH (translated from German)
Frequently asked questions
Who is the Last Planner System suitable for?
For owners, design teams and contractors on projects with several parties. It is easiest to start at project launch, but it also works on a project that is already running.
How long does it take to introduce it?
Introducing the Last Planner System usually takes six weeks, followed by a six-week stabilisation phase.
Can the LPS be combined with BIM or takt planning?
Yes. The LPS can be combined with BIM, takt planning and integrated project delivery (IPD); the approaches complement one another.
Why does the LPS work?
Because the commitments come from the people who carry out the work. Constraints are cleared in advance, and Percent Plan Complete shows every week how reliable the planning was.
What is the Last Planner method?
Last Planner method is another name for the Last Planner System, LPS for short. It means the same thing: the trades plan their sequence together and commit every week to what they will complete.
What is a Last Planner board?
The planning board on which the team plans the weeks ahead. Each trade has a row, each day a column and each task a sticky note. Everyone can see who works where and when, and which task is waiting for another.
What is the difference between the Last Planner System and takt planning?
Takt planning gives the construction sequence a rhythm: equal areas, a fixed order and a fixed time per step. The Last Planner System secures the commitments behind it, week after week. The two methods complement each other.
What does LPS stand for?
LPS stands for Last Planner System. Glenn Ballard and Greg Howell developed the method in the United States in the 1990s.
Key points in brief
- The Last Planner System (LPS) is a Lean Construction method for planning construction work.
- Planning runs from the bottom up: the trades commit themselves to what will be finished in the coming week.
- Five steps: master and phase scheduling set the frame; lookahead planning, weekly work planning and learning repeat every week.
- Percent Plan Complete (PPC) shows every week how reliable the commitments were.
- Variances are analysed without blame; this makes every week more reliable.
Terms used in this article
- Percent Plan Complete (PPC)
- Share of the committed tasks that were completed in the week.
- Make-ready
- Removing constraints in advance: a task only enters the weekly work plan once materials, information and approvals are ready.
- Six-week lookahead
- A rolling view of the next 42 days in which constraints are removed before they disrupt the workflow.
- Weekly work plan
- Firm commitments from all trades for the next five to seven days.
- Reasons for variance
- Variance analysis: categorised reasons why a commitment was not kept. The basis for kaizen.
- Pull planning
- Planning back from the goal: what has to be finished so that the next step can begin?
Further reading
From knowledge to practice
- Practise in a seminar: Last Planner System (in German)8 hours · in person
- Introduce it on your own project (in German)Support from PLACE until the team works with it on its own
- When the project stalls (in German)Assess the situation together
Sources and literature
- Ballard, G., & Howell, G. (2003). Lean project management. Building Research & Information, 31(2), 119-133.
- Koskela, L., & Ballard, G. (2006). Should project management be based on theories of economics or production? Building Research & Information, 34(2), 154-163.
- Ballard, G. (2000). The Last Planner System of Production Control. Dissertation, University of Birmingham.
A question about the Last Planner System?
PLACE is a Lean Construction consultancy from Germany, based in Cologne and Stuttgart. We coach project teams until they work with methods such as the Last Planner System on their own; responsibility for the project stays with the team. Write to us or call us, in English or German. We usually reply within one working day.